Update on Birdville Elementary School

Birdville Elementary School

Our work continues on Birdville Elementary School in Haltom City.

Furthermore, on Saturday, we had the roof top units set with the aid of a helicopter. It is always amazing to watch the precision of those helicopter pilots! We are also wrapping up the masonry work throughout the interior and exterior of the building.

We would like to thank Project Manager Tanner Whitson, Project Engineer Jaime Norton, and Superintendent Coy Rhine – as well as their team and subs – for their hard work. The school is looking terrific and we are on track for an August completion date.

Helicoptor at Birdville

Save

Birdville Elementary School Update

We are on schedule to top out block by the end of the month. We installed half the MEP and we are ready to begin hanging sheetrock.

There’s a slight schedule delay due to the rain and freezing temperatures, but our subs have worked extremely hard to gain those days back. We would specifically like to recognize J&E Masonry who has been a tremendous help on this project.

Now that we are looking at a good stretch of clear weather, we should gain even more days back.