We are on schedule to top out block by the end of the month. We installed half the MEP and we are ready to begin hanging sheetrock.
There’s a slight schedule delay due to the rain and freezing temperatures, but our subs have worked extremely hard to gain those days back. We would specifically like to recognize J&E Masonry who has been a tremendous help on this project.
Now that we are looking at a good stretch of clear weather, we should gain even more days back.